Eighty-one launches. Seventy-three landings. About 214 tonnes of hardware delivered to the Moon's south pole. That is the full shopping list behind NASA's Moon Base program, as New Space Economy tallied it from the agency's own Moon Base User's Guide, and every one of those flights is a place where a schedule can slip. In March 2026, NASA Administrator Jared Isaacman put the headline price at about $20 billion over seven years. This article separates what NASA has formally announced from what it hopes for and what independent analysts doubt. Then it walks through the three hardware gates that must open before any base exists.
Quick Answer
NASA plans a three-phase base near the lunar south pole, with about $20 billion covering the first two phases. First come a 2027 docking test in Earth orbit, working orbital refuelling with uncrewed landings, and the Artemis IV crewed landing.
Key Takeaways
- Isaacman's $20 billion figure covers only phases one and two; CNN described the complete base at around $30 billion.
- Artemis III is now a 2027 docking test in Earth orbit, and the first crewed landing moves to Artemis IV, targeted for early 2028.
- Both commercial landers depend on moving super-cold propellant between spacecraft in orbit, a step not yet shown at this scale.
- Phase three relies on fission reactors because parts of the south pole sit in permanent shadow.
- The Planetary Society's Casey Dreier doubts $20 billion is enough and calls the timeline aggressive.
Artemis II Gives the Plan a Working Starting Point
Start with what is confirmed. Artemis II launched on April 1, 2026, and carried NASA astronauts Reid Wiseman, Victor Glover and Christina Koch, plus Canadian Space Agency astronaut Jeremy Hansen, around the Moon. NASA's mission blog followed the crew around the far side on April 6 and home to a Pacific splashdown off San Diego on April 10. It was the first crewed flight beyond low Earth orbit since Apollo 17 in 1972, so the base plan now starts from a rocket and a capsule that have actually carried people.
Everything after that needs labels. Here, confirmed means the mission record or a formal NASA document. Claimed means a target set by NASA or a company. Doubted means a named independent analyst or auditor has pushed back. Those labels matter because the plan works like a chain of locked gates, and each one stays shut until the one before it opens.
This is the sequence NASA has described, and every date in it is a target rather than a certainty:
| Gate | What has to happen | Current target |
|---|---|---|
| One | Crewed Orion docking with Starship and Blue Moon test vehicles in Earth orbit (Artemis III) | Summer 2027 |
| Two | Propellant transfer in orbit, then uncrewed lunar landings by both landers | Early 2027 to early 2028 |
| Three | Crewed south pole landing (Artemis IV), then repeat landings | Early 2028 onward |
Gate two overlaps gate one on the calendar, so a slip in refuelling can push back the crewed landing even if the docking test goes perfectly.
Three Phases on Paper, From Scouting to Move-In
The formal NASA Moon Base plan runs in three phases. Phase one, from 2026 to 2028, is about reaching the Moon reliably, program executive Carlos García-Galán said in March, with more robotic landers and scouting of candidate sites near the south pole, The Space Review reported. Phase two, running to about 2031, is where construction starts: bigger cargo landers, crews visiting twice a year, and communications, navigation and power on the surface.
THE EVIDENCEFact: The American Nuclear Society's summary of NASA's plan says phase three would deliver about 150,000 kilograms of payload across 29 launches, with habitats at multiple sites and fission reactors for power. García-Galán said nuclear power is essential for surviving the long lunar night.
Astronomy magazine's breakdown of phase two describes solar power stations above 10 kilowatts, communications towers each covering about 10 kilometres (six miles), and around 60 tonnes of cargo across as many as 24 landings. Regular crew rotations would begin around 2030. Solar can carry that stage, but phase three needs something steadier, because parts of the south pole sit in permanent shadow.
One more confirmed change reshapes the hardware list. NASA has paused Gateway, the station it planned for lunar orbit, and says it will repurpose those parts for the surface effort, CBS News reported. Gateway's power and propulsion module is set to fly with a 20 kilowatt fission reactor as a nuclear electric spacecraft called Space Reactor 1 Freedom, The Space Review reported. NASA aims to launch it toward Mars by the end of 2028, and that date is a claim, not a certainty.
What the $20 Billion Does and Does Not Cover
Isaacman was clear that the $20 billion over seven years covers phases one and two only. CNN reported in June that phase one alone runs to about $10 billion through 2028, and described the complete base at around $30 billion. In May, NASA awarded contracts worth more than $1 billion for lunar rovers and for drones to help map a base site, CNN also reported.
So where does the money come from? Asked in May, Isaacman pointed to a $10 billion appropriation in the 2025 budget reconciliation law, plus 2026 appropriations and the president's 2027 budget request, The Center Square reported. That same request proposed cutting NASA's overall budget by about 23 percent, roughly $5.6 billion, according to ZME Science. NASA argues that pausing Gateway and buying commercial rides frees up enough money anyway.
Now the doubt, with a name on it. Casey Dreier, chief of space policy at the Planetary Society, was asked whether $20 billion would be enough to build and sustain a lunar base. His answer was "probably not," and he called the timeline aggressive given the technical challenges, Tech Times reported.
History gives that caution some weight. In January 2024, NASA's acting Inspector General told Congress that Artemis was projected to top $93 billion through 2025, with each of the first four SLS and Orion launches costing at least $4.2 billion, The Center Square reported. That figure describes the older architecture, not this one. Still, it is a reminder that early human spaceflight estimates have grown before.
Docking and Refuelling Come Before Any Landing
Gate one is Artemis III. NASA announced on February 27, 2026, that the mission would no longer land, and at its October 23 briefing described a 14 to 17 day flight targeted for summer 2027. Four astronauts in Orion will dock with test versions of SpaceX's Starship lander and Blue Origin's Blue Moon a few hundred kilometres (a couple of hundred miles) up. Reporting on the briefing says the mission needs three large rockets for one flight.
THE EVIDENCEImportant: NASA's Office of Inspector General, in a March 2026 audit of the Human Landing System contracts, describes SpaceX's approach as a propellant depot in low Earth orbit filled by more than 10 Starship tanker flights. The audit flags the vehicle-to-vehicle cryogenic propellant transfer test as a source of added schedule pressure.
Gate two is the step nobody has done at this scale: moving large amounts of super-cold propellant from one spacecraft to another in orbit. Both landers need it to reach the Moon, and Artemis III will not test it, Space.com noted. SpaceX plans a separate propellant transfer demonstration in early 2027, Payload reported.
Then come the uncrewed landings. SpaceX aims to land a Starship on the Moon before the end of 2027, and Blue Origin targets a Blue Moon Mark 2 landing in early 2028, according to a NASA lander program briefing reported by Technology.org. These robotic flights, not the astronaut flights, may quietly decide whether there is anything on the surface worth visiting.
Gate Three Is a Cadence Problem, Not One Landing
Gate three is Artemis IV, the crewed landing near the south pole, targeted for early 2028, with Artemis V aimed at late 2028. After that, the real test is repetition. Isaacman wants at least two launch providers and crewed landings every six months, and phase one alone calls for roughly 25 launches and 21 landings by the end of 2028, Tech Times reported.
THE EVIDENCEDo You Know: In November 2023, the US Government Accountability Office concluded that the first crewed Artemis landing was unlikely before 2027. It cited outstanding milestones including in-space cryogenic propellant transfer and confirmation of the performance of Starship's Raptor engines.
To be fair, this order has a logic. Testing docking close to Earth means a crew can get home far faster than from lunar orbit if something goes wrong. Two competing landers mean one delay does not have to ground the whole program.
Now the hard bit. Under the 2019 plan, the first Artemis landing was meant to happen in 2024. NASA says the 2028 target has held since mid-2025, but the mission carrying it has changed, and an early October lander schedule leaves very little slack between the uncrewed landings and the crewed one, Technology.org reported. A delay is not a failure, but in a chain of gates, a delay can travel.
Over the next twelve months, watch for the Starship propellant transfer test in early 2027, Artemis III's docking runs in summer 2027, and the first uncrewed landings from late 2027 into early 2028. Underneath all of it sit the budget negotiations in Congress, which may decide how many of those 73 landings ever get paid for.
Want to see each gate explained the day it flies? Escape Velocity breaks down launches, briefings and data releases, and labels what is confirmed, what is claimed and what is doubted.
Watch the embedded video for the full walk through NASA's three gates, then tell us which one you think slips first. Subscribe to Escape Velocity so you catch the next gate as it opens.
Further Reading
- Flight 15 Double Catch: Why Starship's Heat Shield Matters More
- We Hit an Asteroid in 2022. Now Hera Is Checking the Damage
- Why Interstellar Comet 3I/ATLAS Has Ice Like Worlds Beyond Neptune
Explore Escape Velocity.
Frequently asked questions
Why build the base at the lunar south pole?
NASA's plan concentrates landings near the south pole, where some crater floors sit in permanent shadow. Scientists have long thought those cold traps may hold water ice, which could one day supply water, oxygen or propellant. The same shadows create the power problem, which is why the later phases lean on fission reactors rather than solar panels alone.
Is Gateway cancelled for good?
Officially, NASA has paused Gateway rather than cancelled it, and says the hardware will be repurposed for the surface effort. The clearest example is the power and propulsion module, set to become the nuclear electric spacecraft Space Reactor 1 Freedom. Whether a lunar orbit station returns later depends on future plans and budgets, which nobody can promise today.
Will astronauts live on the Moon full time?
Not in the near term. Phase two plans crews visiting about twice a year, with regular rotations starting around 2030, and phase three adds habitats at multiple sites in the early 2030s. A continuously crewed outpost would depend on cargo landings, power and funding all arriving on schedule, so treat permanence as a goal rather than a fixed date.
Does Congress have to approve the money?
Yes. NASA requests funds, but Congress writes the appropriations each year. The $10 billion from the reconciliation law helps, yet the 2027 request also proposed cutting NASA's overall budget by about 23 percent. Priorities can shift between budget cycles, so the annual appropriations bills are worth watching as closely as the launches themselves.
How can I follow progress without getting caught up in hype?
Look for formal NASA documents, mission briefings and audit reports from NASA's Inspector General or the GAO, and treat company dates as targets. When a test ends early, check what data came back before calling it a failure. Schedule changes often surface weeks after the hardware results, not on launch day.